Air Handler Shutdown and Pressure Adjustment on 4th Floor from 7/25 to 7/29

On 7/25, the Hensel Phelps contractor shut down all air handler units on the 4th floor to test the pressure required to open the doors. However, the main air handler unit on the 4th floor failed to restart. With a major loss of air supply to the 4th floor, all room air differentials were affected. Positive-pressure rooms became less positive, and negative-pressure rooms became more negative as a result. Once the air handler was replaced on Monday, 7/29, the air pressures returned to their original range.
 
notion image

 
 

▶️ Recent 7-day graph of the Anteroom air pressure differential

notion image
 

New graphs with higher granular y-axis and MIN/MAX line indicators (from 7/17/2024 to 7/28/2024)

 

Anteroom Door Sensitivity Adjusted to Close Quicker

 

Non-HD Door Sensitivity Adjusted to Close Quicker

 

HD Door Sensitivity Adjusted to Close Quicker

 

Audible Alarm After 30 Seconds

 

Removed tape residue

notion image
 

Clear silicone seal behind the mirror in the anteroom

notion image
 

Clear silicone seal behind the signs in the buffer rooms

notion image
 

Clear silicone in crevices around non-HD passthrough box

notion image
 

Eye glass lens cleaner wipes

notion image
 

Sealed grummet holes on sides of hoods

notion image